Tasks Scheduling (medium)
Problem Statement
There are ‘N’ tasks, labeled from ‘0’ to ‘N-1’. Each task can have some prerequisite tasks which need to be completed before it can be scheduled.
Given the number of tasks and a list of prerequisite pairs, find out if it is possible to schedule all the tasks.
Examples
Example 1:
Input: Tasks=6, Prerequisites=[2, 5], [0, 5], [0, 4], [1, 4], [3, 2], [1, 3]
Output: true
Explanation: A possible scheduling of tasks is: [0 1 4 3 2 5]
Example 2:
Input: Tasks=3, Prerequisites=[0, 1], [1, 2]
Output: true
.....
.....
.....